06/12 2015

Joncaire St Steps Reconstruction Project Update

The City recently finished their geo-tech study of the site; the study revealed that the existing steps are slowly sliding down the hill. In order to address this, building the new steps will require core drilling into the bedrock. 

The current project timeline is:

  • Design completion by December 2015.
  • The project will be bid out in January 2016.
  • Demolition will begin Winter 2016.
  • Construction will finish Spring 2016.