03/07 2015

Birmingham Bridge Construction And Detours Mar 9 – Nov 11

The next phase of the Birmingham Bridge Complex Preservation Project was announced Friday by PennDOT.
Starting at 10 p.m. March 13, the northbound lanes of the bridge will be closed. All northbound traffic will be shifted into the southbound lanes. The new configuration will have two southbound lanes, one northbound lane and a bicycle lane. Pedestrians will use the southbound sidewalk.
The northbound Oakland/Forbes Avenue ramp will be closed.
CAR AND TRUCK DETOUR:
  • Northbound traffic will turn left onto Fifth Avenue
  • Turn left onto Moultrie Street
  • Turn left onto Forbes Avenue
PennDOT plans to have the configuration in place until Nov. 11. Preparatory work will begin March 9-13.
PennDOT is creating an email distribution list to keep motorists informed of all traffic advisories and construction updates. Enroll by sending email addresses to stcowan@pa.gov and writing “Subscribe – Birmingham Bridge” in the subject line. Additionally, motorists can find information at http://birmingham.otmapgh.org/

2 thoughts on “Birmingham Bridge Construction And Detours Mar 9 – Nov 11”

  1. […] SCHEDULE CHANGE: Birmingham Bridge Preservation begins New Phase Monday Morning in Pittsburgh   Pittsburgh – PennDOT District 11 is announcing the next phase of work on the Birmingham Bridge Complex Preservation Project in the City of Pittsburgh, Allegheny County, will begin Monday morning, March 16 weather permitting. (Originally the phase change was set to begin Friday night).   Beginning at 5 a.m. Monday morning, the northbound side of the Birmingham Bridge will close to traffic to begin preservation work.  All northbound traffic will be shifted into the southbound lanes.  The new configuration will consist of one 12 foot wide northbound lane, two 11 foot wide southbound lanes and a bicycle lane.  Additionally, all pedestrians will use the southbound sidewalk. See previous post for more project info and links […]

  2. […] SCHEDULE CHANGE: Birmingham Bridge Preservation begins New Phase Monday Morning in Pittsburgh   Pittsburgh – PennDOT District 11 is announcing the next phase of work on the Birmingham Bridge Complex Preservation Project in the City of Pittsburgh, Allegheny County, will begin Monday morning, March 16 weather permitting. (Originally the phase change was set to begin Friday night).   Beginning at 5 a.m. Monday morning, the northbound side of the Birmingham Bridge will close to traffic to begin preservation work.  All northbound traffic will be shifted into the southbound lanes.  The new configuration will consist of one 12 foot wide northbound lane, two 11 foot wide southbound lanes and a bicycle lane.  Additionally, all pedestrians will use the southbound sidewalk. See previous post for more project info and links […]

Comments are closed.